Construction Update

To date, the foundations for both of the new units have been dug, with associated soil removal, and the steel frame has been erected for the first unit. In addition to this, the acoustic fence along the boundary with our neighbours has been installed.

The key activities that will be happening over the next few months include:

  • Erecting the steel frame for the second unit with a crane – w/c 11 July – w/c 8 August
  • Installing bricks/blockwork for the second unit – w/c 25 July – w/c 22 August
  • Installing roof cladding for the second unit – w/c 22 August – w/c 19 September
  • Laying the ground floor for the first unit – w/c 22 August – w/c 12 September

Please note that the above timings are approximate and could change.

Whilst we don’t expect the above activities to have an adverse effect on our neighbours, if you do experience any issues, or have any questions about the work being carried out, please contact our community liaison team using the details below.